Monitor to testify on Georgia nuclear plant progress
Dec 18, 2012 | 703 views | 0 0 comments | 2 2 recommendations | email to a friend | print
In this Tuesday, Dec. 11, 2012 photo, an earth mover works on a new nuclear reactor at the Plant Vogtle nuclear power plant in Augusta, Ga. (AP Photo/John Bazemore)
In this Tuesday, Dec. 11, 2012 photo, an earth mover works on a new nuclear reactor at the Plant Vogtle nuclear power plant in Augusta, Ga. (AP Photo/John Bazemore)
slideshow
ATLANTA (AP) — A state-hired monitor will soon give an update about Southern Co.'s progress building a new nuclear power plant in Georgia.

Nuclear engineer Williams Jacobs Jr. is scheduled to testify Tuesday about the construction of Plant Vogtle (VOH'-gohl) near Augusta. Jacobs is monitoring construction of the $14 billion facility for the state's Public Service Commission, which regulates utilities.

The first reactor was supposed to be finished on April 1, 2016, with the second reactor following a year later. In his latest report, Jacobs said the first reactor will probably be ready no sooner than June 2017. He said the cost of a one-year delay is in the range of hundreds of millions of dollars.

Southern Co. officials say they are still in talks with their contractors about the building schedule.